Fire Stations Construction Updates

Fire Station 6

Fire Station 6

  • Fire Station 6 is one day under contract deadline.
  • Due for July 2022 for completion.
  • All steel construction and concrete has begun.
  • CMU work has been initiated.
  • Most material has been purchased and stored on/off site.  
  • Minor change orders pending approval for the addition of cameras and the SCBA Compressor.
  • Contractors have been proactive on materials.

Fire Station 9

  • Steel Erection 
  • CMU’s installation is ongoing
  • Electrical, plumbing, mechanical rough in on-going
  • Setting up Reinforcement for CMU Walls
  • Start Grading at the drive Entrance
  • Start grading the truck exit drive
  • Project has tentatively been extended to 4-13-2022, initial completion date was 3-21-22.
  • Metal Roof Panels (Delay)